AI compute buildout and capital fact sheet

Facts as of November 25, 2026

A FutureSearch fact sheet: dated facts and trajectories from public sources, gathered for forecasting. Each line carries its date and names or links its source. It contains no forecasts. Where a company or one of its leaders is quoted, the line records what they said.

Each line carries its date and ends with its sources. Nvidia's results, share price and governance are in the Nvidia fact sheet. Each lab's own compute commitments, sites and suppliers are in the OpenAI fact sheet, the Anthropic fact sheet, the Google DeepMind fact sheet and the SpaceX fact sheet; the share prices of SpaceX and Anthropic are in their sheets. Federal AI law is in the AI policy fact sheet. Market values below are closing prices times the shares outstanding reported on the companies' filing covers, our arithmetic unless a source is named.

1. Alphabet: capital spending, guidance and financing

  • Alphabet capital expenditures (cash purchases of property and equipment, calendar quarters; quarters after the first in each year are year-to-date differences, our arithmetic): $12.0B (Q1 2024) → $13.2B (Q2) → $13.1B (Q3) → $14.3B (Q4 2024) → $17.2B (Q1 2025) → $22.4B (Q2) → $24.0B (Q3) → $27.9B (Q4 2025) → $35.7B (Q1 2026) → $44.9B (Q2) → $51.4B (Q3 2026); full years $52.5B (2024) and $91.4B (2025); $132.0B in the first nine months of 2026 (10-Q filed Oct 29, 2026). [data.sec.gov, sec.gov]
  • Alphabet 2026 capex guidance, CFO Anat Ashkenazi on its calls: $175B to $185B, "with investments ramping over the course of the year" (Feb 4, 2026) → $180B to $190B, "to now include investment related to the acquisition of Intersect, which closed in March" (Apr 29) → $195B to $205B, "primarily due to an acceleration in the delivery of capacity to meet growing demand" (Jul 22) → "remain unchanged" (Oct 28). On 2027: "we expect our 2027 CapEx to significantly increase compared to 2026" (Apr 29) → "We continue to expect our CapEx to increase significantly in 2027, and we'll provide further details on our Q4 call" (Oct 28). [s206.q4cdn.com 1, 2, 3, 4]
  • Alphabet's CFO on the Q3 2026 call (Oct 28, 2026): about 65% of Q3 technical-infrastructure investment was servers and networking equipment (useful lives of six years) and 35% data centers (7 to 40 years); free cash flow was -$9.1B in Q3 and $19.7B over twelve months, also reduced by inventory built for TPU system sales, which she called "not the traditional kind of CapEx". [s206.q4cdn.com]
  • Alphabet leases signed but not yet commenced, "primarily related to data centers and energy infrastructure" (future lease payments, undiscounted): $75.6B (Mar 31, 2026) → $85.2B (Jun 30) → $130.5B (Sep 30, 2026), commencing between 2026 and 2031 with terms of one to 26 years (10-Qs). [sec.gov 1, 2, 3]
  • Alphabet long-term debt at face value: $49.1B (Dec 31, 2025) → $127.5B (Sep 30, 2026), the 2026 notes comprising $45.0B in US dollars and the equivalent of $10.2B in euros, $7.3B in sterling (maturities out to 2126), $6.0B in Canadian dollars, $3.9B in Australian dollars, $3.7B in Swiss francs and $3.7B in yen (10-Q filed Oct 29, 2026). [sec.gov]
  • Alphabet note sales after Sep 30, 2026: €6B closed Nov 5 and C$6B closed Nov 24 (8-Ks). [sec.gov, sec.gov]
  • Alphabet equity raised in June 2026 (10-Q filed Oct 29, 2026): net proceeds of $20.5B from a public offering of class A and C shares and $10.0B from a private placement with Berkshire Hathaway, and $19.0B from 6.25% mandatory convertible preferred stock issued June 5, the last "for general corporate purposes, including capital expenditures to scale AI infrastructure and global compute". [sec.gov]

2. Amazon: capital spending, guidance and financing

  • Amazon purchases of property and equipment (cash, gross, calendar quarters): $17.6B (Q2 2024) → $22.6B (Q3) → $27.8B (Q4 2024, a year-to-date difference, our arithmetic) → $25.0B (Q1 2025) → $32.2B (Q2) → $35.1B (Q3) → $39.5B (Q4 2025, our arithmetic) → $44.2B (Q1 2026) → $54.2B (Q2) → $77.3B (Q3 2026); full years $83.0B (2024) and $131.8B (2025); $175.7B in the first nine months of 2026 (10-Q filed Oct 30, 2026). [data.sec.gov, sec.gov]
  • Amazon purchases of property and equipment net of proceeds from sales and incentives, trailing twelve months (the figure its free cash flow uses): $103.0B (to Q2 2025) → $115.9B (Q3 2025) → $128.3B (Q4 2025) → $147.3B (Q1 2026) → $169.0B (Q2 2026) → $210.7B (Q3 2026); in Q3 2026 alone, $77.3B of purchases less $1.4B of proceeds and incentives. Amazon says the increase "primarily reflects investments in artificial intelligence" (Q3 release, Oct 29, 2026). [sec.gov]
  • Amazon 2026 capex expectation, CEO Andy Jassy: "about $200 billion in capital expenditures across Amazon in 2026" (Q4 2025 release, Feb 5, 2026) → "approximately $220 billion in cash CapEx in 2026", "The higher cost of memory pushing this number up from our prior estimate of about $200 billion" (call of Jul 30) → "We continue to expect 2026 cash capital expenditures to be approximately $220 billion" (Q3 release, Oct 29) and "expect to spend meaningfully more in 2027" (call of Oct 29). The CFO put Q3 2026 "cash CapEx" at $75.9B, which equals purchases of property and equipment less proceeds and incentives (calls as transcribed by Motley Fool). [sec.gov 1, 2 · fool.com 1, 2]
  • Amazon on capacity (calls as transcribed by Motley Fool): "we will still not have enough capacity to meet all the demand we have in 2026", "this dynamic will also be true in 2027, too" and "we expect to have double the power capacity by the end of 2027 that we had in 2025" (Jassy, Jul 30, 2026); AWS "Backlog is $578 billion, growing triple digits year-over-year" (Jassy, Oct 29, 2026). [fool.com, fool.com]
  • Andy Jassy, Amazon's CEO, on CNBC (Nov 17, 2026, CNBC's unofficial transcript): "we expect to spend around $220 billion this year in CapEx and that we expect to spend meaningfully more next year"; "the big chunks of compute are largely reserved for us in '27 and a good chunk of that in '28"; its chips business was "over a $25 billion annual revenue run rate" at the last quarterly call, "growing triple digits year over year". [cnbc.com]
  • Amazon property and equipment acquired under finance leases (not in the purchases figure): $1.5B in Q3 2026 and $4.5B in the twelve months to Sep 30, 2026; property and equipment acquired but not yet paid rose $26.8B over the same twelve months (Q3 release, Oct 29, 2026). [sec.gov]
  • Amazon leases not yet commenced (undiscounted payments, commitments table): $96.4B (Dec 31, 2025) → $137.2B (Jun 30, 2026) → $164.9B (Sep 30, 2026); at Sep 30 it also listed $159.6B of commitments for property and equipment and $94.8B of unconditional purchase obligations (10-K and 10-Qs). [sec.gov 1, 2, 3]
  • Amazon free cash flow, trailing twelve months: $18.2B (to Q2 2025) → $14.8B (Q3 2025) → $11.2B (Q4 2025) → $1.2B (Q1 2026) → -$7.6B (Q2 2026) → -$42.4B (Q3 2026) (Q3 release, Oct 29, 2026). [sec.gov]
  • Amazon long-term debt raised in 2026: proceeds of $115.1B in the first nine months, $48.1B of it in Q3 (cash-flow statement); note sales closed $37.0B (Mar 13, eleven tranches with coupons of 3.85% to 6.05%, maturities 2028 to 2076) → €14.5B (Mar 16) → C$14.0B (Jun 12) → $25.0B (Jul 9, coupons of 4.60% to 6.25%) → £4.25B (Sep 14) (8-Ks). [sec.gov 1, 2, 3, 4, 5, 6]

3. Microsoft: capital spending, guidance and financing

  • Microsoft additions to property and equipment (cash; fiscal years end June 30): $14.9B (FY25 Q1, quarter to Sep 30, 2024) → $15.8B (Q2) → $16.7B (Q3) → $17.1B (Q4, a year-to-date difference, our arithmetic) → $19.4B (FY26 Q1, to Sep 30, 2025) → $29.9B (Q2) → $30.9B (Q3) → $35.8B (Q4, to Jun 30, 2026, our arithmetic) → $39.4B (FY27 Q1, to Sep 30, 2026); fiscal years $64.6B (FY2025) and $115.9B (FY2026) (10-Q filed Oct 28, 2026; 10-K filed Jul 29, 2026). [data.sec.gov, sec.gov]
  • Microsoft right-of-use assets obtained for finance-lease liabilities (leases that commenced; not in the cash figure): $4.3B (FY25 Q1) → $6.4B → $3.2B → $6.5B (FY25 Q4) → $9.1B (FY26 Q1) → $6.3B → $4.0B → $5.1B (FY26 Q4) → $5.2B (FY27 Q1, to Sep 30, 2026); $20.5B in FY2025 and $24.6B in FY2026 (10-Q and 10-K). [data.sec.gov, sec.gov]
  • Microsoft's stated capital expenditures, which count finance leases at their full principal value when a lease commences (CFO Amy Hood on each call; finance leases in brackets): $22.6B (FY25 Q2, to Dec 31, 2024) → $21.4B (FY25 Q3) → $24.2B (FY25 Q4, $6.5B) → $34.9B (FY26 Q1, to Sep 30, 2025, $11.1B) → $37.5B (FY26 Q2, $6.7B) → $31.9B (FY26 Q3, $4.7B) → $41B (FY26 Q4, to Jun 30, 2026, $5.6B, "including the impact from higher component pricing") → $45.2B (FY27 Q1, to Sep 30, 2026, $7.4B, "as some third-party capacity deliveries we expected in Q1 were delayed"); roughly three quarters of FY27 Q1 spending went to short-lived assets, "primarily CPUs and GPUs". [microsoft.com 1, 2, 3, 4, 5, 6, 7, 8]
  • Microsoft's capex outlook, CFO Amy Hood: "we now expect the FY26 growth rate to be higher than FY25" (Oct 29, 2025) → for calendar 2026, "roughly $190 billion", "which includes approximately $25 billion from the impact of higher component pricing" (Apr 29, 2026) → "approximately $175 billion" after a change in data-center useful lives shifted future leases from finance to operating leases, and "we expect FY27 capital expenditures will grow year-over-year given demand signals across our portfolio" (Jul 29) → "In Q2, we expect CapEx spend will be over $50 billion" and "for the calendar year, spend should be approximately $170 billion due to the 3P capacity delays" (Oct 28, 2026); Q1 FY27 had been guided at "over $50 billion". [microsoft.com 1, 2, 3, 4]
  • Microsoft on demand (Oct 28, 2026): "Customer demand continues to exceed available supply"; commercial remaining performance obligation "grew 73% to $677 billion", with "a weighted average duration of 2.3 years". [microsoft.com]
  • Microsoft leases "primarily for datacenters" that had not yet commenced: $155.1B (Dec 31, 2025) → $196.6B (Mar 31, 2026) → $329.1B (Jun 30) → $364.6B (Sep 30, 2026), "with some arrangements subject to certain contractual conditions being met", commencing between fiscal 2027 and fiscal 2034 with terms of 1 to 20 years (10-Qs and 10-K). [sec.gov 1, 2, 3, 4]
  • Microsoft note sale (8-K, Nov 4, 2026): $25.0B of notes under an underwriting agreement of Oct 29, 2026, ten tranches from floating-rate notes due 2028 to 6.350% notes due 2066. [sec.gov]

4. Meta: capital spending, guidance and financing

  • Meta capital expenditures including principal payments on finance leases (Meta's reported measure; quarters after the first in each year are year-to-date differences, our arithmetic): $8.5B (Q2 2024) → $9.2B (Q3) → $14.8B (Q4 2024) → $13.7B (Q1 2025) → $17.0B (Q2) → $19.4B (Q3) → $22.1B (Q4 2025) → $19.8B (Q1 2026) → $31.1B (Q2) → $34.9B (Q3 2026; "$34.91 billion" in the release of Oct 21, 2026); full-year 2025 $72.2B; $85.8B in the first nine months of 2026. [data.sec.gov 1, 2 · sec.gov]
  • Meta 2026 capex outlook, including principal payments on finance leases (its quarterly releases): $115B to $135B (Jan 28, 2026) → $125B to $145B, reflecting "higher component pricing this year and, to a lesser extent, additional data center costs to support future year capacity" (Apr 29) → $130B to $145B (Jul 29) → $135B to $145B (Oct 21). On 2027 (Oct 21): "Looking beyond 2026, we are still developing our budget and capacity plans for next year, but we expect to continue investing aggressively to support both our core business and emerging AI initiatives." [sec.gov 1, 2, 3, 4]
  • Meta Q3 2026 (release, Oct 21, 2026): free cash flow negative $2.12B; cash, cash equivalents and marketable securities $82.45B at Sep 30; headcount 66,775, down 15% from a year earlier; total consolidated indebtedness $83.7B at Sep 30, 2026 (prospectus supplement, Oct 28). [sec.gov, sec.gov]
  • Meta operating and finance leases not yet commenced, mostly data centers: about $103.77B (Dec 31, 2025) → $182.88B (Mar 31, 2026) → $278.99B (Jun 30) → $355.73B (Sep 30, 2026), commencing through 2036 with terms of up to 30 years; non-cancelable contractual commitments were $454.52B at Sep 30, 2026 (10-K and 10-Qs). [sec.gov 1, 2, 3, 4]
  • Meta's unconsolidated data-center ventures, in each of which it holds 20% (10-Q filed Oct 22, 2026): Louisiana, about $27B of estimated development costs, with Meta's lease commencing in 2029, and Texas (entered July 2026), about $14B, lease commencing in 2028; each lease runs four years with renewals up to 20; Meta's maximum residual value guarantees to them rose from $28.1B (Dec 31, 2025) to $41.5B (Sep 30, 2026) and its maximum exposure to loss from $46.0B to $68.4B. [sec.gov]
  • Meta financing in 2026: $25.0B of notes (8-K, May 4) → 6.50% mandatory convertible preferred depositary shares, net proceeds about $12.5B, and a concurrent class A share sale under forward agreements at $622.92 a share, about $24.9B of net proceeds on settlement "on or prior to November 19, 2027" (prospectus supplements, Oct 28) → $15.0B of notes in five tranches with coupons of 5.850% (2031) to 7.500% (2056) (closed Nov 5) → €9.0B of notes in six tranches (closed Nov 12). [sec.gov 1, 2, 3, 4]

5. Oracle: capital spending, backlog, ratings and financing

  • Oracle capital expenditures (cash; fiscal years end May 31): $2.3B (FY25 Q1, quarter to Aug 31, 2024) → $4.0B (Q2) → $5.9B (Q3) → $9.1B (Q4) → $8.5B (FY26 Q1, to Aug 31, 2025) → $12.0B (Q2) → $18.6B (Q3) → $16.5B (Q4, to May 31, 2026) → $28.5B (FY27 Q1, to Aug 31, 2026); fiscal years $21.2B (FY2025) and $55.7B (FY2026); free cash flow -$23.7B in FY2026 and -$5.0B in FY27 Q1 (release, Sep 10, 2026). [data.sec.gov, sec.gov]
  • Oracle capex guidance: fiscal 2026 "capital expenditures of $50 billion", "unchanged from our most recent previous guidance" (release, Mar 10, 2026), against $55.7B reported and a "net cash outlay for capital expenditures" (capex less certain short-term financing and customer prepayments) of $47.7B; fiscal 2027, CFO Hilary Maxson: "We continue to anticipate $90 billion to $95 billion in CapEx for the full year" with "not more than $70 billion in net cash CapEx" (call of Sep 10, 2026, as transcribed by Motley Fool), after a net cash outlay of $18.0B in the quarter to Aug 31, 2026. [sec.gov 1, 2 · fool.com]
  • Oracle's financing plan (release, Jun 10, 2026): "In fiscal year 2027, Oracle expects to raise approximately $40 billion through a combination of debt and equity financing including its previously announced $20 billion at-the-market equity issuance. Oracle does not expect to issue additional debt in calendar year 2026." On Sep 10 the CFO said Oracle "completed our previously disclosed $20 billion equity issuance in entirety during the Q1"; Oracle then closed sales of $10B of notes and $10B of common stock on Nov 4, 2026. [sec.gov 1, 2 · fool.com]
  • Oracle remaining performance obligations: $99.1B (Aug 31, 2024) → $97.3B (Nov 30, 2024) → $130.2B (Feb 28, 2025) → $137.8B (May 31, 2025) → $455.3B (Aug 31, 2025) → $523.3B (Nov 30, 2025) → $552.6B (Feb 28, 2026) → $638.0B (May 31, 2026) → $664.0B (Aug 31, 2026) (10-Qs and 10-Ks); the CFO said on Sep 10, 2026: "We now expect around half of our RPO to convert into sales over the next 36 months" (Motley Fool transcript). [data.sec.gov · sec.gov · fool.com]
  • Oracle lease commitments not yet on its balance sheet, "substantially all related to data center arrangements": $260B (May 31, 2026) → $288B (Aug 31, 2026), expected to commence between fiscal 2027 and fiscal 2029 with terms of 15 to 19 years; at May 31 they included a lease for which Oracle guaranteed up to $3.3B of the lessor's borrowing, maturing September 2026 (10-K and 10-Q). [sec.gov, sec.gov]
  • Oracle FY27 Q1 (release, Sep 10, 2026): revenue $19.3B, up 30%; cloud infrastructure revenue $7.4B, up 121%; "Oracle booked more than $30 billion of additional AI cloud contracts in Q1"; it delivered "850MW additional datacenter capacity" and, since the end of Q4, "more than 300,000 GPUs"; "the Company confirms there is no incremental impact on its plans to raise capital". [sec.gov]
  • Oracle ratings: S&P lowered Oracle's long-term rating to BBB-, its lowest investment-grade grade, on Jul 9, 2026, with a stable outlook, citing "mounting debt and sharply negative cash flow"; Moody's has a negative outlook on Oracle's rating (Computing, in an undated article citing a Bloomberg report of Jul 16, 2026; Fortune, Sep 18, 2026, for S&P). Fortune reported on Sep 18 that Oracle's five-year credit default swap spreads were "recently greater than 200 basis points", a level last reached in 2008. [fortune.com, computing.co.uk]
  • Oracle financing in 2026: $25B of notes with coupons of 4.550% to 6.850% (closed Feb 4) and an at-the-market program to sell up to $20.0B of common stock (agreement of Feb 2), of which $19.9B was sold, net, in the quarter to Aug 31, 2026 → $10B of common stock (86,206,897 shares) and $10B of notes with coupons of 7.000% (2029) to 8.650% (2046), both closed Nov 4, 2026 (8-Ks; FY27 Q1 cash-flow statement). [sec.gov 1, 2, 3]
  • Oracle has listed depositary shares of 6.50% Series D mandatory convertible preferred stock, from an underwriting agreement of Feb 2, 2026 for 100,000,000 depositary shares (8-K, Feb 5, 2026). [sec.gov]

6. Apple and other companies' capital spending

  • Apple payments for property, plant and equipment (cash; fiscal years end in late September): $11.0B (FY2023) → $9.4B (FY2024) → $12.7B (FY2025) → $9.0B (FY2026, to Sep 26, 2026); quarterly in FY2026, $2.37B (to Dec 27, 2025) → $1.97B → $2.46B → $2.24B (to Sep 26, 2026; the last three are year-to-date differences, our arithmetic) (10-K filed Nov 3, 2026). [data.sec.gov, sec.gov]
  • CoreWeave's and Nebius's capital spending and guidance are in sections 15 and 16; SpaceX's compute build-out, and the "approximately $44 billion of senior and subordinated notes to fund the purchase of GPUs and related equipment for SpaceX" priced by Apollo and Goldman Sachs on Nov 20, 2026, are in the SpaceX fact sheet. [sec.gov 1, 2 · apollo.com]

7. Data-center capacity: trackers and their readings

  • Epoch AI's AI data-center hub (updated Nov 23, 2026): 96 sites with 15.1 GW of IT power and 15.8 million H100-equivalents, and 19.6 GW of total facility power; Epoch estimates the hub covers 43% of global deployed AI computing capacity as of Nov 25, 2026 (90% interval 29% to 77%). Of the 96 sites, 77 are in the US with 12.6 GW of IT power (our sum of the hub's data file). [epoch.ai, epoch.ai]
  • Epoch AI's sites summed by date (our arithmetic on the per-site IT power in the hub's timelines file, read Nov 25, 2026; these are Epoch's current estimates of each site's history, not what the hub showed at the time): 2.0 GW (Dec 31, 2024) → 4.0 GW (Jun 30, 2025) → 6.8 GW (Dec 31, 2025) → 8.4 GW (Mar 31, 2026) → 12.2 GW (Jun 30) → 14.0 GW (Sep 30) → 15.1 GW (Nov 25, 2026); for the US sites, 1.8 → 3.4 → 5.7 → 6.9 → 10.4 → 12.0 → 12.6 GW. [epoch.ai, epoch.ai]
  • CBRE, North America Data Center Trends H1 2026 (Aug 27, 2026; eight primary markets): supply grew 33.7% from a year earlier to a record (the release prints "10.9 megawatts (MW)"); 7,481 MW under construction, a record; vacancy 1.4%, unchanged from year-end 2025; net absorption 1,456 MW; more than 80% of capacity under construction preleased, against 74.3% a year earlier. [cbre.com]
  • JLL, North America data center report, midyear 2026 (Aug 11, 2026; all markets including what it calls frontier markets): "66 GW under construction, 95% of which is pre-committed"; "25 GW of absorption" in H1 2026; vacancy at 1%; frontier markets "77% of all capacity under development"; Northern Virginia "nearly 7 GW of inventory". [jll.com]
  • Cushman & Wakefield, Americas Data Center Update H1 2026 (Sep 14, 2026): 50.3 GW operational in the Americas, 94.1% of it in the US; 37.7 GW under construction, a record, 91.7% of it pre-committed; 285 GW planned; vacancy 3.8%. [cushmanwakefield.com]
  • Currence, Data Center Outlook Q3 2026 (undated page): the 2026 to 2030 pipeline "has nearly doubled to more than 100GW, but most of it remains speculative"; "0.5GW came online this quarter, up from zero in Q2, led by Microsoft's Fairwater Phase 1"; natural-gas on-site power had 1.5 GW online and 11 GW under construction. [currence.ai]

8. The largest AI data-center campuses outside the Stargate and SpaceX sites

  • Anthropic-Amazon New Carlisle, Indiana (Amazon-owned, used by Anthropic; Amazon's Project Rainier), the largest site in Epoch AI's hub, IT power by Epoch's estimates from imagery: 398 MW (Jun 23, 2025, Buildings 1-7) → 626 MW (Dec 23, 2025) → 910 MW (Mar 23, 2026) → 1,037 MW (Oct 19, 2026, Buildings 17-18); land clearing began Feb 9, 2024. [epoch.ai, epoch.ai]
  • Meta Prometheus, New Albany, Ohio, IT power by Epoch AI's estimates: 76 MW (Oct 14, 2025, Building 1) → 368 MW (Jan 18, 2026, Buildings 2-6) → 471 MW (Aug 31, 2026, Buildings 7-10, which are tents). Meta Hyperion, Richland Parish, Louisiana: land clearing began Dec 20, 2024, and Epoch's hub showed no operating IT power on Nov 25, 2026. [epoch.ai, epoch.ai]
  • Microsoft Fairwater Atlanta (Georgia), IT power by Epoch AI's estimates: 321 MW (Oct 14, 2025, Buildings 1-2) → 636 MW (Jun 14, 2026, Buildings 3-4). Microsoft Fairwater Wisconsin (Mount Pleasant): Building 1 operational Apr 16, 2026, 369 MW (Epoch, citing a post by Satya Nadella). [epoch.ai]
  • Google's largest sites in Epoch AI's hub (current IT power, read Nov 25, 2026): Pryor (North), Oklahoma 368 MW; New Albany, Ohio 333 MW; Columbus, Ohio 303 MW; Bristow 238 MW; Council Bluffs (East), Omaha and Papillion 237 MW each. [epoch.ai]
  • Other large sites in Epoch AI's hub: CoreWeave Denton, Texas, 8 MW (May 31, 2025) → 67 MW (Dec 31, 2025) → 131 MW (Feb 23, 2026) → 262 MW (Jul 3, 2026); Anthropic Lake Mariner, Barker, New York (a TeraWulf site), 42 MW (May 31, 2026) → 210 MW (Oct 31, 2026); Amazon Madison Mega Site 284 MW; in Malaysia, DayOne Nusajaya 473 MW and DayOne Kempas 422 MW (current IT power, read Nov 25, 2026). [epoch.ai, epoch.ai]
  • OpenAI's Stargate sites and SpaceX's Colossus sites, with Epoch AI's readings, are in the OpenAI and SpaceX fact sheets. [epoch.ai]

9. Power: ERCOT, PJM and FERC

  • ERCOT (Jun 18, 2026): "ERCOT is tracking more than 438,000 MW of large load requests, nearly 89 percent from data centers alone"; Texas regulators approved its "Batch Zero" process, which "groups qualified large projects that are 75 megawatts (MW) and greater into a single study"; Batch Zero applicants were to learn their classification in August 2026, and Batch 1 applications "are expected to open in Summer 2027". [ercot.com]
  • PJM capacity auctions, both at the FERC-approved price cap: 2027/28 delivery year (results Dec 17, 2025), $333.44/MW-day for 134,479 MW, 6,623 MW short of the reliability requirement, a reserve margin of 14.8% against the 20% needed, with "Nearly 5,100 MW" of a 5,250 MW rise in forecast peak "attributable to data center demand" → 2028/29 (Jul 14, 2026), $325/MW-day for 138,318 MW, 6,831 MW short; each cost $16.4B. [insidelines.pjm.com, insidelines.pjm.com]
  • PJM's 2029/30 capacity auction is set for Dec 9 to Dec 15, 2026; state ratepayer advocates (including offices in Pennsylvania, Ohio and New Jersey) and PJM's market monitor had asked by Nov 19 that it wait "until data center loads, both real and speculative, can be removed from the load forecast"; PJM declined: "Postponing the auction this close to its execution could destabilize the market" (Utility Dive, Nov 19, 2026). [utilitydive.com]
  • FERC on large loads: in June 2026 it issued show-cause orders telling the regional grid operators to propose rules for connecting large loads or explain why theirs are just and reasonable; ISO New England answered on Nov 13 and PJM, CAISO, MISO and NYISO on Nov 16, 2026, with SPP due by Nov 20; PJM proposed a "Fast Energization Process" studying large loads and generation together within a year (Utility Dive, Nov 17, 2026). [utilitydive.com]

Grid operators' own load forecasts

  • ERCOT's preliminary long-term load forecast (Apr 15, 2026; ERCOT's projection): "approximately 367,790 MW of demand in the ERCOT Region by 2032"; its CEO, Pablo Vegas: "we believe this forecast to be higher than expected future load growth"; the all-time peak it cited is 85,508 MW (Aug 10, 2023). [ercot.com]
  • PJM's 2026 long-term load forecast (Jan 14, 2026; PJM's projection): summer peak of 183,008 MW in 2030 (875 MW, 0.5%, below the 2025 forecast) → 216,872 MW in 2035 (6,949 MW, 3.3%, above) → about 222,000 MW in 2036 → above 253,000 MW in 2046; 10-year summer growth of 3.6% a year, with data-center growth the main reason for the higher long-term outlook. [insidelines.pjm.com]

10. Power: utilities' data-center load and nuclear agreements

  • AEP (Q3 2026, reported Oct 29, 2026): contracted load through 2031 of 84 GW, "up 22% from 69 GW in the previous quarter", led by "a 10.4-GW data center in Ohio being developed by SB Energy"; retail electric sales rose 11% in Q3. [utilitydive.com]
  • Dominion Energy (CFO on the Oct 30, 2026 call, reported Nov 2): "over 12 GW of capacity contracted under electric service agreements" and 54.9 GW of data-center capacity "in various stages of contracting". [utilitydive.com]
  • Southern Company (reported Nov 13, 2026): signed large-load contracts of 21 GW, with another 7 GW "in late stages across Alabama, Georgia and Mississippi"; of a 75 GW pipeline, an executive said: "Now, are we going to land 75 GW of projects? Probably not." [utilitydive.com]
  • Hyperscalers' nuclear agreements as compiled by the Carnegie Endowment (Jun 2, 2026): up to about 13 GW announced, about 6.9 GW through power purchase agreements for existing plants (including restarts, life extensions and uprates) by the early 2030s and about 6.1 GW through direct partnerships, mainly small modular and advanced reactors, by the mid-2030s, the latter depending on developers delivering commercially. [carnegieendowment.org]
  • Nuclear agreements by company, as stated by the companies and compiled by Carnegie (Jun 2, 2026): Microsoft, 835 MW from the Crane Clean Energy Center (Three Mile Island Unit 1), due back in service in 2027; Amazon, 1.9 GW from Talen through 2042 at full volume by 2032, and about 5 GW of X-energy projects targeted by 2039; Meta, 1,121 MW from Constellation's Clinton plant over 20 years, 2.6 GW from Vistra plants (January 2026, pending NRC approval), up to 2.8 GW from TerraPower by 2035 and a 1.2 GW Oklo campus in Ohio by 2034; Alphabet, 500 MW from Kairos Power by 2035 (the first 50 MW, Hermes-2, in 2030) and 1.8 GW at three Elementl sites by 2035; Oracle had announced no nuclear developer partnership. [carnegieendowment.org]

11. State and local moratoria and siting laws

  • Quorum's count (Oct 26, 2026): it "reviewed 486 state data center measures" from 2025 and 2026, of which 42 became law; no legislature has enacted a data-center moratorium into law; New York is the only state with a statewide moratorium, by executive order; moratorium bills appeared in 11 states (elsewhere in the article, "at least 10"). [quorum.us]
  • New York Executive Order 62 (signed Jul 14, 2026): for facilities that "consume or can consume 50 megawatts of energy or more", the Department of Environmental Conservation holds in abeyance applications for discretionary permits not determined complete before the order, "Until DPS submits its report of the final Generic Environmental Impact Statement and associated findings statement"; permits from local governments are not affected. [governor.ny.gov]
  • New York's Responsible Data Center Development Act (S10642, passed as A11560 on Jun 4, 2026; Senate vote 43-17): it bars state environmental permits for data centers with peak demand of 20 MW or more for one year after it takes effect, except projects already under construction; the Senate's bill page recorded no delivery to the governor, signature or veto (read Nov 25, 2026). [nysenate.gov]
  • Maine LD 307, which would have placed "a temporary limitation on certain data centers": vetoed by the governor on Apr 24, 2026; veto sustained Apr 29 (72-65 in the House, per Quorum). [legislature.maine.gov, quorum.us]
  • State data-center laws signed or effective in 2026, as listed by Quorum (Oct 26): South Dakota SB 135 and HB 1038 (Mar 30), Utah HB 76 (effective Mar 23), Idaho H.895 (Apr 2), Mississippi SB 3410 (Apr 8), Alabama SB 270 (Apr 17), Nebraska LB 1010 (Apr 17), Maine LD 713 (Apr 23), Tennessee HB 1847 and Florida SB 484 (May 7), Oklahoma HB 2992 (May 11), Washington SB 6231 (Jun 11), West Virginia HB 4983 (Jun 29), New Jersey A.796 (Jul 7), Delaware SB 312 (Aug 26), New Jersey S.3379 and S.4390 (Aug 27), California SB 1168 and AB 2469 (Sep 21). [quorum.us]
  • Local opposition (Data Center Watch, Q2 2026 report): "At least 45 projects worth $68 billion were disrupted by local opposition in Q2 2026", and "Communities nationwide imposed data center development moratoriums"; the report gives no count of local moratoria. [datacenterwatch.org]

12. GPU rental prices

  • Silicon Data H100 index (Bloomberg ticker SDH100RT; a standardized hourly rate per GPU from neoclouds and GPU marketplaces): $2.00 (Dec 9, 2025) → $2.20 (Jan 6, 2026) → $2.63 (start of April) → $2.47 (Apr 8) → $2.59 (end of April) → $2.73 (May 31) → $2.75 (Sep 30) → $3.06 (Nov 10, "highest level since at least January 2025") → $3.08 (read Nov 25); quarterly averages $2.62 (Q2 2026) and $2.69 (Q3). [silicondata.com 1, 2, 3, 4]
  • Silicon Data H100 hyperscaler index (hyperscalers' on-demand rates): $7.44 (start of April 2026) → $7.51 (end of April) → $7.46 (May 31) → $7.20 (Sep 30) → $7.06 (read Nov 25); quarterly averages $7.45 (Q2) and $7.21 (Q3). [silicondata.com 1, 2, 3]
  • Silicon Data's other indexes, per GPU-hour (read Nov 25, 2026): B200 $6.99, B300 $7.72, H200 $3.66, A100 $1.64, A100 at hyperscalers $3.92, MI300X $2.78; quarterly averages for H200 $2.82 (Q2) and $3.19 (Q3), for A100 $1.54 (Q2) and $1.62 (Q3). [silicondata.com, silicondata.com]
  • Ornn Compute Price Index, H100 SXM (volume-weighted executed on-demand rental prices in USD per GPU-hour; "Reserved-capacity, long-term, and forward contracts are outside the scope"; public history from Aug 26, 2026): $2.91 (Aug 31) → $2.69 (Sep 30) → $3.00 (Oct 31) → $3.16 (Nov 24); monthly means $2.83 (September), $2.94 (October) and $3.15 (Nov 1-24), range $2.46 to $3.53 (our arithmetic on Ornn's daily values). [data.ornn.com, data.ornn.com]
  • Ornn Compute Price Index, B200: $6.16 (Aug 31, 2026) → $8.05 (Sep 30) → $9.54 (Oct 31) → $9.07 (Nov 24); monthly means $7.26 (September), $8.51 (October) and $9.50 (Nov 1-24), high $9.94 (Nov 8) (our arithmetic on Ornn's daily values). [data.ornn.com]
  • AWS EC2 Capacity Blocks for ML list prices (read Nov 25, 2026): 8x H100 (p5.48xlarge) $47.757 an hour, $5.970 per accelerator-hour (US East Atlanta Local Zone); H200 $6.866, B200 $14.208 and B300 $16.146 per accelerator-hour; "The current prices are scheduled to be updated next in January, 2027." [aws.amazon.com]
  • CoreWeave, as reported by Silicon Data (Nov 16, 2026): on its Nov 10 call it said pricing for its prior-generation Ampere and Hopper fleet rose 30% to 50% from the prior quarter, above original contract prices, and that more than 130,000 GPUs come off contract in 2027 and about 170,000 in 2028. [silicondata.com]

13. Memory prices and high-bandwidth-memory supply

  • TrendForce's measured conventional DRAM contract prices: up 45-50% from the prior quarter in 4Q25 (50-55% blended with HBM; release of Feb 26, 2026) → up about 93-98% in 1Q26 (Jun 1, 2026); DRAM industry revenue $53.58B in 4Q25 (+29.4%) → about $97B in 1Q26 (+81%). The 1Q26 release says SK hynix's price growth was held back by "declining HBM contract prices in 2026". [trendforce.com, trendforce.com]
  • TrendForce DRAM spot prices (Nov 25, 2026, 18:10 Taipei time; the page states no unit): DDR5 16Gb (2Gx8) 4800/5600 session average 60.767, day's range 45.50 to 72.00, down 0.11%; DDR4 16Gb (2Gx8) 3200 77.75; DDR4 8Gb (1Gx8) 3200 43.214. [trendforce.com]
  • Micron (call of Sep 30, 2026, on its fiscal Q4): DRAM prices rose in the "high teens percentage range" and NAND "approximately 30%" in the quarter; "We have completed agreements for the vast majority of our calendar 2027 HBM bit supply", at prices "much higher than 2026 prices"; 26 strategic customer agreements, "over 35% of our revenue through 2030"; conditions "much tighter in fiscal 2027 and 2028 than they were in 2026"; revenue $54.2B in fiscal Q4 2026 and guidance of $61.5B ± $1.5B for fiscal Q1 2027, whose results call is set for Dec 17, 2026, 2:30 p.m. Mountain time. [investing.com, stocktitan.net]
  • Samsung (Q3 2026 call, Oct 29 in Korea): DRAM average selling price up "20% level" and NAND "high teens" in Q3; HBM4 sales more than tripled from Q2 to 60% of HBM sales; "our 2027 HBM supply volume is already sold out at an agreed target price"; "we expect tight supply conditions to continue in 2028"; 2026 capex expected at 84.4 trillion won, 29 trillion won of it in Q3. [investing.com]
  • SK hynix (Q3 2026 results, Oct 28, 2026): revenue about 104.6 trillion won and operating profit about 83.3 trillion won; it expects "the structure in which demand exceeds supply to persist through 2030"; long-term agreements with 14 major customers cover "more than 50% of total production capacity for 2027 and 2028"; HBM4 expected to pass HBM3E in shipments and revenue in Q4; its M15X fab to run at full capacity by year-end. [news.skhynix.com]
  • Server component lead times (TrendForce, Apr 15, 2026): PCB and CPU lead times "now extending to nearly one year"; BMC IC lead times up from 11-16 weeks to 21-26 weeks. [trendforce.com]

14. TSMC: revenue, AI demand, capacity and capex

  • TSMC monthly net revenue in 2026 (NT$ billions, unaudited): 401.26 (Jan) → 317.66 (Feb) → 415.19 (Mar) → 410.73 (Apr) → 416.98 (May) → 442.68 (Jun) → 467.58 (Jul) → 514.81 (Aug) → 511.86 (Sep) → 586.89 (Oct, 59.7% above October 2025 and 14.7% above September, the latter our arithmetic); January to October NT$4,485.62B, up 43.3%. [investor.tsmc.com]
  • TSMC monthly net revenue in 2025 (NT$ billions, unaudited): 293.29 (Jan) → 260.01 → 285.96 → 349.57 → 320.52 → 263.71 → 323.17 → 335.77 → 330.98 → 367.47 (Oct) → 343.61 → 335.00 (Dec); full year 3,809.05, up 31.6%. [investor.tsmc.com]
  • TSMC's next monthly reports (financial calendar, "subject to change"): November 2026 revenue on Dec 10, 2026 and December 2026 revenue on Jan 8, 2027; no Q4 2026 results date was listed (read Nov 25, 2026). [investor.tsmc.com]
  • TSMC Q3 2026 (release, Oct 15, 2026): revenue NT$1,494.24B (US$46.72B), up 41.2% from a year earlier in US dollars; gross margin 66.4%, operating margin 58.7%; 3nm 33%, 5nm 28%, 7nm 10% and 2nm 8% of wafer revenue; Q4 guidance US$52.3B to US$54.3B at 31.8 NT$ per US$. [pr.tsmc.com]
  • TSMC's high-performance computing platform: 55% of Q4 2025 revenue (call of Jan 15, 2026, as relayed by MarketBeat) → 68% of Q3 2026 revenue (The Next Web, Oct 17, 2026). [finance.yahoo.com, thenextweb.com]
  • TSMC's 2026 capital budget: $52B to $56B (Jan 15, 2026, as relayed by MarketBeat) → $60B to $64B, "unchanged" on Oct 15, 2026 (Focus Taiwan; The Next Web); its CFO said spending in 2026 to 2028 would be "significantly higher than in the previous three years". [finance.yahoo.com · focustaiwan.tw · thenextweb.com]
  • TSMC on demand (Oct 15, 2026): it raised its expected 2026 revenue growth to about 44% in US dollars, from "slightly more than 40 percent" in July (Focus Taiwan); C.C. Wei: "we are being prudent in our business planning going into 2027", citing consumer and price-sensitive segments (The Next Web); TSMC said it would "ensure sufficient CoWoS capacity to meet their demand" (Focus Taiwan). In January it had raised its own projection of AI accelerator revenue growth to a mid-to-high-50s percent compound annual rate for 2024 to 2029 (MarketBeat). [focustaiwan.tw · thenextweb.com · finance.yahoo.com]
  • TSMC's board (Nov 10, 2026): capital appropriations of about US$40.93B for advanced technology capacity, advanced packaging, mature and specialty capacity, fab construction, and 2027 R&D and sustaining capital; up to US$500M each to buy Anthropic common shares at its IPO price and OpenAI preferred stock; up to US$500M to set up an investment company. [pr.tsmc.com]

15. CoreWeave: revenue, backlog, customers, debt and capacity

  • CoreWeave quarterly revenue (10-Q and 10-K; Q4 2025 is the annual figure less nine months, our arithmetic): $0.98B (Q1 2025) → $1.21B (Q2) → $1.37B (Q3) → $1.57B (Q4 2025) → $2.08B (Q1 2026) → $2.58B (Q2) → $3.66B (Q3 2026). [data.sec.gov, sec.gov]
  • CoreWeave remaining performance obligations (10-Q and 10-K): $14.7B (Mar 31, 2025) → $30.1B (Jun 30) → $50.0B (Sep 30, 2025) → $60.7B (Dec 31, 2025) → $98.8B (Mar 31, 2026) → $103.7B (Jun 30) → $132.3B (Sep 30, 2026), of which 36% is expected to be recognized within 24 months, 38% in months 25 to 48 and the rest in months 49 to 86 (10-Q filed Nov 12, 2026). Its release of Nov 10, 2026 puts "revenue backlog", which adds other amounts it expects under committed contracts, at about $132.5B. [data.sec.gov · sec.gov 1, 2]
  • CoreWeave customer concentration (10-Q filed Nov 12, 2026): "Customer A" was 67% of revenue in Q3 2025 and 24% in Q3 2026, and "Customer B" 30% in Q3 2026 (33% and 26% over the first nine months of 2026); the filing says the letters "may represent different customers than those reported in a previous period", names Microsoft and OpenAI as other significant customers, and cites Jane Street's commitment of about $6.0B (April 2026). [sec.gov]
  • CoreWeave deferred revenue: $4.1B (Dec 31, 2024) → $8.2B (Dec 31, 2025) → $10.0B (Sep 30, 2026); in Q3 2026 "$1.9 billion of the deferred revenue balance from the beginning of the period was reclassified from deferred revenue to customer liabilities ... as contracts became cancellable during the quarter" (10-Q filed Nov 12, 2026). [sec.gov]
  • CoreWeave debt (10-Q filed Nov 12, 2026): recourse debt, net, $20.7B (Dec 31, 2025) → $41.6B (Sep 30, 2026), plus about $5.3B of non-recourse debt; total principal of $47.5B falls due $2.4B in the rest of 2026, $11.0B in 2027, $5.5B in 2028, $4.7B in 2029, $4.2B in 2030 and $19.6B later; effective interest rates run from 2% to 3% on convertible notes to 15% on its oldest delayed-draw term loan; the company was "in compliance with all covenants". [sec.gov]
  • CoreWeave debt raised in 2026 (10-Q filed Nov 12, 2026): $2.8B of 9.75% senior notes due 2031 and $4.0B of convertible notes due 2032 (April); $1.3B of 9.625% senior notes and €2.0B of senior notes, both due 2032 (June); $4.2B of convertible notes due 2033 (September); delayed-draw term loan facilities of $3.1B (DDTL 5.0) and $2.6B (DDTL 5.5, drawable through Dec 31, 2026). [sec.gov]
  • CoreWeave interest expense, net, in Q3 2026 rose $536M (173%) from Q3 2025; it expects Q4 2026 interest expense of $1.05B to $1.15B (release, Nov 10, 2026). [sec.gov, sec.gov]
  • CoreWeave cash purchases of property and equipment (cash-flow statements; Q2, Q3 and Q4 figures are year-to-date differences, our arithmetic): $1.4B (Q1 2025) → $2.5B (Q2) → $2.4B (Q3) → $4.1B (Q4 2025) → $7.7B (Q1 2026) → $6.4B (Q2) → $9.4B (Q3 2026). CoreWeave raised the low end of its 2026 capital-expenditure guidance from $35B to $37B, to a range of "$37 billion to $39 billion", "as a result of our expectation to deploy infrastructure and deliver it to customers sooner than planned" (Nov 10, 2026). [data.sec.gov, sec.gov]
  • CoreWeave power (Q3 2026 release, Nov 10, 2026): it "Added more than 200 MWs of active power to reach over 1.7 GW", grew "total contracted power more than 900 MW to over 4.6 GW", more than 1.3 GW of it outside the US, and expects "more than 1.85 gigawatts of active power at year-end". [sec.gov]
  • CoreWeave guidance (Nov 10, 2026): 2026 revenue $13.0B to $13.3B (raised), adjusted operating income $1.275B to $1.375B, and annualized run-rate revenue of $20B to $21B exiting 2026. [sec.gov]
  • CoreWeave (CRWV) month-end closes: $71.61 (Dec 31, 2025) → $93.19 (Jan 30, 2026) → $79.56 (Feb 27) → $77.47 (Mar 31) → $111.60 (Apr 30) → $109.53 (May 29) → $99.54 (Jun 30) → $71.77 (Jul 31) → $84.89 (Aug 31) → $87.12 (Sep 30) → $54.87 (Oct 30) → $42.57 (Nov 25); record close $183.58 (Jun 20, 2025); 2026 high $137.98 (May 6), low $39.51 (Nov 20), 71.4% below the 2026 high; market value about $23.7B at the Nov 25 close on 556.1M class A and B shares (Oct 30 filing cover; our arithmetic). [finance.yahoo.com, sec.gov]

16. Nebius, Lambda and other GPU clouds

  • Nebius Q3 2026 (shareholder letter, Nov 12, 2026): group revenue $981M, up 571% from a year earlier; "Prepayments on Q3 agreements covered more than 100% of the associated capex", up from 50-60% in Q2; $12B of total contract value signed since the start of Q3. [sec.gov]
  • Nebius guidance (Nov 12, 2026): 2026 revenue "at the low end of our $3.0-3.4 billion range", with an adjusted EBITDA margin of about 40%; "the ARR we guided to for December" now expected "to arrive in February"; for 2027, revenue of $12B to $13B, capex of $40B to $45B, "pre-tax breakeven by the end of 2027", more than 1 GW of new capacity each year, and prepayments and financing against investment-grade contracts to cover 75% to 85% of 2027 capex. [sec.gov]
  • Nebius financing in 2026 (6-Ks): an upsized $5.0B private offering of convertible senior notes, priced Aug 20 (launched at $4.5B) and closed by Aug 24 → a $3.5B senior secured bridge term loan from Citibank for "the buildout of the Borrowers' GPU infrastructure capacity", at Term SOFR plus 2.75% rising 0.25% every 90 days after Oct 17, 2026 to 3.50%, maturing Oct 16, 2027 (6-K, Oct 22). [sec.gov 1, 2, 3]
  • Nebius (NBIS) month-end closes: $83.71 (Dec 31, 2025) → $85.19 (Jan 30, 2026) → $91.19 (Feb 27) → $103.76 (Mar 31) → $138.23 (Apr 30) → $231.09 (May 29) → $276.17 (Jun 30) → $190.41 (Jul 31) → $206.32 (Aug 31) → $235.88 (Sep 30) → $154.14 (Oct 30) → $84.99 (Nov 25); 2026 high $286.69 (Jun 18), low $81.31 (Nov 20), 71.6% below the high. [finance.yahoo.com]
  • Lambda has no registration statement on EDGAR; the last filing by Lambda, Inc. is a Form D notice of an exempt offering dated Feb 16, 2024 (EDGAR, read Nov 25, 2026). Bloomberg reported on Aug 10, 2026 that Lambda took loans for an Nvidia-tied chip deal (headline relayed by StackedAI, which puts the loans at $917M). [sec.gov, stackedai.net]
  • Anthropic's own filings on its Lambda and Nscale contracts, and OpenAI's, Google's and Anthropic's contracts with SpaceX's compute business, are in the Anthropic, OpenAI and SpaceX fact sheets. [sec.gov]

17. Defaults and distress among AI-infrastructure borrowers

  • Defaults: the amcompute tracker of GPU and neocloud defaults (updated Oct 17, 2026) says "No neocloud has publicly defaulted on a GPU-backed loan", that it found no public record of a GPU-backed loan being foreclosed and its GPUs auctioned, and that "No GPU-focused neocloud has filed for bankruptcy as of October 2026"; no later public case was found through Nov 25, 2026. [amcompute.com]
  • Character.AI, an AI application developer and a buyer of compute rather than a GPU cloud, said late on Oct 12, 2026 that it had filed for Chapter 11; Disney agreed to pay $20M for a license to its intellectual property, a sale was expected by late November or early December, and its CEO cited "significant legal, regulatory and operational headwinds" (CBS News, Oct 13). The amcompute tracker, citing Bloomberg Law, puts the filing in Delaware with assets and liabilities each estimated at $50M to $100M. [cbsnews.com, amcompute.com]
  • Earlier GPU-cloud stress listed by the amcompute tracker (updated Oct 17, 2026): CoreWeave cut its 2025 revenue guidance on Nov 10, 2025 after a third-party data-center developer fell behind, with the customer keeping the full contract value; Fermi's first prospective tenant ended a $150M advance agreement in December 2025. [amcompute.com]
  • Federal Reserve Board, Financial Stability Report (Nov 13, 2026; information as of Oct 28): in its survey of 23 market contacts in September and October, "AI was the top-cited risk, with responses noting concerns around elevated equity valuations, AI-enabled cyberattacks, and complex forms of AI-related financing", and respondents "widely cited the risk of a sharp correction in AI-related equities, driven by uncertain returns on large capital expenditures." [federalreserve.gov]
  • Fed Financial Stability Report (Nov 13, 2026), on debt: "Advanced computing–related debt issuance rose to more than $680 billion by October 2026, about a fivefold increase from $130 billion in all of 2023"; its share of nonfinancial investment-grade corporate debt issuance went "from less than 6 percent in 2023 to about 31 percent in 2026"; "Outstanding public debt related to advanced computing is estimated at more than $1.1 trillion as of October 2026" (Bank of America and Bloomberg data, counting Rule 144A deals but not other private placements). [federalreserve.gov]
  • Fed Financial Stability Report (Nov 13, 2026), on obligations beyond debt: for Alphabet, Amazon, Broadcom, Meta, Microsoft, Nvidia and Oracle at 2026:Q2, leases not yet commenced have undiscounted values above $1 trillion and take-or-pay contracts, residual value guarantees and similar obligations above $2 trillion, growing faster than their debt; the largest US bank holding companies have "close to $1 trillion of exposure to large technology firms, data center developers, advanced computing–related SPEs and private credit vehicles, and utility companies". [federalreserve.gov]
  • Fed Financial Stability Report (Nov 13, 2026), on valuations: "Measures of equity valuations have remained high, partly driven by market enthusiasm for super intelligence (SI)"; the forward price-to-earnings ratio of the S&P 500 "remained well above its historical median", though rising earnings expectations had pushed it down over the past year. [federalreserve.gov]
  • European Central Bank, Financial Stability Review (Nov 18, 2026): "Risks from AI valuations, fiscal imbalances and geoeconomic tensions cloud the financial stability outlook"; "AI-related debt issuance has surged, potentially contributing to rising global bond yields"; "Equity valuation measures, notably of US tech firms, have moderated considerably"; equity issuance funding the AI boom "is now on track to surpass the dotcom bubble peak as a share of US GDP." [ecb.europa.eu, ecb.europa.eu]
  • Bank of England Financial Policy Committee record (Sept 30, 2026; meeting of Sept 25): "Equity valuations for AI companies fell sharply in July"; "The risk of a sharper correction persists, notably if there is a more significant shock to earnings expectations"; the record cites a Morgan Stanley estimate that global AI-related debt issuance in 2026 was about $450 billion as of early September, "more than double the total issuance in all of 2025", and says AI hyperscalers accounted for 47% of sterling corporate bond issuance so far in 2026. [bankofengland.co.uk]
  • International Monetary Fund, Global Financial Stability Report "Resilience, Risk, and Transformation" (Oct 13, 2026): weaker or less durable investment and profitability in AI "could lead to a correction" in AI-related asset prices, and "Corrections could be amplified by rising leverage and concentrated exposures." [imf.org]

19. Market values of the largest AI-exposed listed companies

  • Apple market value at month-end closes: $4.02T (Dec 31, 2025) → $3.81T (Jan 30, 2026) → $3.88T (Feb 27) → $3.73T (Mar 31) → $3.99T (Apr 30) → $4.58T (May 29) → $4.25T (Jun 30) → $4.51T (Jul 31) → $4.62T (Aug 31) → $4.86T (Sep 30) → $5.01T (Oct 30) → $5.17T (Nov 25, $355.58); high close $356.27 (Nov 13, 2026, about $5.18T); largest 2026 fall 12.7%, from $315.20 (Jun 2) to $275.15 (Jun 25). [finance.yahoo.com · sec.gov · companiesmarketcap.com]
  • Microsoft market value at month-end closes: $3.59T (Dec 31, 2025) → $3.20T (Jan 30, 2026) → $2.92T (Feb 27) → $2.75T (Mar 31) → $3.03T (Apr 30) → $3.34T (May 29) → $2.77T (Jun 30) → $3.45T (Jul 31) → $3.77T (Aug 31) → $3.81T (Sep 30) → $3.88T (Oct 30) → $3.64T (Nov 25, $489.93); record close $555.80 (Nov 4, 2026, about $4.13T), then 12.8% lower by Nov 20 ($484.52); largest 2026 fall 27.0%, from $483.47 (Jan 7) to $352.83 (Jun 25). [finance.yahoo.com · sec.gov · companiesmarketcap.com]
  • Alphabet market value at month-end closes (class A and B shares at the GOOGL price, class C at GOOG; share counts from the April, July and October 2026 10-Q covers): $3.80T (Dec 31, 2025) → $4.10T (Jan 30, 2026) → $3.78T (Feb 27) → $3.48T (Mar 31) → $4.65T (Apr 30) → $4.59T (May 29) → $4.31T (Jun 30) → $4.36T (Jul 31) → $4.13T (Aug 31) → $4.19T (Sep 30) → $3.43T (Oct 30) → $3.35T (Nov 25, GOOGL $273.10); high close May 13, 2026 (GOOGL $402.62, about $4.86T); low Nov 20 (GOOGL $265.29, about $3.25T), 33% below the high. [finance.yahoo.com · sec.gov · companiesmarketcap.com]
  • Amazon market value at month-end closes: $2.47T (Dec 31, 2025) → $2.57T (Jan 30, 2026) → $2.25T (Feb 27) → $2.24T (Mar 31) → $2.85T (Apr 30) → $2.91T (May 29) → $2.56T (Jun 30) → $2.93T (Jul 31) → $2.80T (Aug 31) → $2.69T (Sep 30) → $2.60T (Oct 30) → $2.64T (Nov 25, $244.43); record close $284.02 (Aug 3, 2026, about $3.06T), then 15.4% lower by Oct 30 ($240.35); largest 2026 fall 19.6%, from $247.38 (Jan 9) to $198.79 (Feb 13). [finance.yahoo.com · sec.gov · companiesmarketcap.com]
  • Meta market value at month-end closes (class A and B shares; share counts from the April and October 2026 10-Q covers): $1.68T (Dec 31, 2025) → $1.82T (Jan 30, 2026) → $1.65T (Feb 27) → $1.45T (Mar 31) → $1.55T (Apr 30) → $1.61T (May 29) → $1.43T (Jun 30) → $1.41T (Jul 31) → $1.45T (Aug 31) → $1.84T (Sep 30) → $1.57T (Oct 30) → $1.56T (Nov 25, $609.89); 2026 high close $777.59 (Sep 24, about $1.97T), then 27.9% lower by Nov 20 ($560.84); record close $790.00 (Aug 12, 2025); largest 2026 fall 28.8%, from $738.31 (Jan 29) to $525.72 (Mar 27). [finance.yahoo.com · sec.gov · companiesmarketcap.com]
  • Broadcom market value at month-end closes: $1.64T (Dec 31, 2025) → $1.57T (Jan 30, 2026) → $1.51T (Feb 27) → $1.47T (Mar 31) → $1.98T (Apr 30) → $2.13T (May 29) → $1.80T (Jun 30) → $1.85T (Jul 31) → $1.77T (Aug 31) → $1.68T (Sep 30) → $1.56T (Oct 30) → $1.44T (Nov 25, $300.86); record close $481.57 (Jun 2, 2026, about $2.29T); low $291.53 (Nov 5), 39.5% below the record. [finance.yahoo.com · sec.gov · companiesmarketcap.com]
  • TSMC market value at its New York ADR month-end closes (5.185B ADR-equivalent units, the basis companiesmarketcap.com uses; our arithmetic): $1.58T (Dec 31, 2025, $303.89) → $1.71T (Jan 30, 2026) → $1.94T (Feb 27) → $1.75T (Mar 31) → $2.05T (Apr 30) → $2.17T (May 29) → $2.48T (Jun 30) → $2.10T (Jul 31) → $2.15T (Aug 31) → $2.37T (Sep 30) → $2.11T (Oct 30) → $1.78T (Nov 25, $342.34); record close $485.80 (Oct 5, 2026, about $2.52T); low $318.71 (Nov 20), 34.4% below the record. [finance.yahoo.com, companiesmarketcap.com]
  • Oracle market value at month-end closes: $0.56T (Dec 31, 2025) → $0.47T (Jan 30, 2026) → $0.42T (Feb 27) → $0.42T (Mar 31) → $0.46T (Apr 30) → $0.65T (May 29) → $0.42T (Jun 30) → $0.37T (Jul 31) → $0.43T (Aug 31) → $0.42T (Sep 30) → $0.40T (Oct 30) → $0.32T (Nov 25, $103.88, on 3.11B shares after its November offering); record close $328.33 (Sep 10, 2025); 2026 high $248.15 (Jun 1, about $0.71T); low $101.19 (Nov 20), 59.2% below the 2026 high and 69.2% below the record. [finance.yahoo.com · sec.gov 1, 2 · companiesmarketcap.com]
  • AMD market value at month-end closes: $0.35T (Dec 31, 2025) → $0.39T (Jan 30, 2026) → $0.33T (Feb 27) → $0.33T (Mar 31) → $0.58T (Apr 30) → $0.84T (May 29) → $0.95T (Jun 30) → $0.78T (Jul 31) → $0.77T (Aug 31) → $1.00T (Sep 30) → $0.83T (Oct 30) → $0.67T (Nov 25, $406.03); record close $649.42 (Oct 6, 2026, about $1.06T); low $404.40 (Nov 5), 37.7% below the record. [finance.yahoo.com · sec.gov · companiesmarketcap.com]
  • Micron market value at month-end closes: $0.32T (Dec 31, 2025) → $0.47T (Jan 30, 2026) → $0.46T (Feb 27) → $0.38T (Mar 31) → $0.58T (Apr 30) → $1.10T (May 29) → $1.30T (Jun 30) → $0.93T (Jul 31) → $1.08T (Aug 31) → $1.20T (Sep 30) → $1.00T (Oct 30) → $0.68T (Nov 25, $601.25); record close $1,213.56 (Jun 25, 2026, about $1.37T); low $594.51 (Nov 20), 51.0% below the record. [finance.yahoo.com · sec.gov · companiesmarketcap.com]
  • PHLX Semiconductor index (SOX) at month-end closes: 7,083.13 (Dec 31, 2025) → 7,998.47 (Jan 30, 2026) → 8,098.37 (Feb 27) → 7,588.20 (Mar 31) → 10,503.70 (Apr 30) → 12,829.38 (May 29) → 14,246.96 (Jun 30) → 11,311.08 (Jul 31) → 11,535.05 (Aug 31) → 12,628.62 (Sep 30) → 10,688.80 (Oct 30) → 8,774.86 (Nov 25); record close 14,634.72 (Jun 22, 2026); low 8,408.59 (Nov 20), 42.5% below the record. [finance.yahoo.com]
  • Nasdaq-100 index at month-end closes: 25,249.85 (Dec 31, 2025) → 25,552.39 (Jan 30, 2026) → 24,960.04 (Feb 27) → 23,740.19 (Mar 31) → 27,452.12 (Apr 30) → 30,333.18 (May 29) → 30,276.35 (Jun 30) → 28,274.20 (Jul 31) → 29,456.97 (Aug 31) → 30,408.50 (Sep 30) → 28,384.85 (Oct 30) → 26,046.90 (Nov 25); record close 31,224.47 (Oct 6, 2026); low 25,028.98 (Nov 20), 19.8% below the record. [finance.yahoo.com]
  • S&P 500 index at month-end closes: 6,845.50 (Dec 31, 2025) → 6,939.03 (Jan 30, 2026) → 6,878.88 (Feb 27) → 6,528.52 (Mar 31) → 7,209.01 (Apr 30) → 7,580.06 (May 29) → 7,499.36 (Jun 30) → 7,489.72 (Jul 31) → 7,686.14 (Aug 31) → 7,651.54 (Sep 30) → 7,580.07 (Oct 30) → 7,182.78 (Nov 25); record close 7,818.93 (Oct 6, 2026); low 6,910.39 (Nov 20), 11.6% below the record. [finance.yahoo.com]

20. Industry-wide compute: chip capacity across labs and clouds

  • Total available AI chip computing capacity across designers "has grown by approximately 3.3x per year since 2022" (90% interval 2.7x to 4.1x), a doubling time of about seven months, with Nvidia chips over 60% of the total (Epoch AI, Jan 9, 2026; chip-sales data updated Feb 16, 2026). [epoch.ai]
  • Cumulative capacity of AI chips sold, by Epoch AI's estimates (Nov 18, 2026): peak 8-bit compute of about 12 million H100-equivalents (Q2 2025) → about 32 million (Q2 2026), 2.6x; "agentic inference capacity", measured with Epoch's Inference Performance Index on long, cached-context workloads, about 1.45 million GB300-equivalents → about 6.67 million, 4.6x. [epoch.ai]

Easy to misread

  1. Capex bases differ. The cash-flow series here (Alphabet, Amazon, Microsoft, Oracle, Apple, CoreWeave) leave out equipment taken on finance leases. Microsoft's stated capex adds finance leases at full value when they commence (FY27 Q1: $45.2B stated, $39.4B cash), and its July 2026 useful-life change moves future leases to operating leases, outside capex; Meta's measure adds principal payments on finance leases; Amazon's "cash capex" nets proceeds and incentives off gross purchases (Q3 2026: $75.9B against $77.3B); Oracle's "net cash outlay" also nets customer prepayments and some financing (FY2026: $47.7B against $55.7B). [microsoft.com 1, 2 · sec.gov 1, 2, 3]
  2. Fiscal years. Microsoft's fiscal year ends June 30 (fiscal 2027 began Jul 1, 2026), Oracle's May 31 (fiscal 2027 began Jun 1, 2026) and Apple's in late September; Alphabet, Amazon, Meta and CoreWeave report calendar years. [sec.gov 1, 2, 3]
  3. Derived quarters. Cash-flow statements report year-to-date totals, so quarters marked as differences are our arithmetic from the filed figures and can differ by rounding from figures stated on earnings calls. [data.sec.gov]
  4. Leases not yet commenced are undiscounted future payments under signed leases, mostly for data centers, and are not capital spending or debt; each company words and scopes them differently (Microsoft's include arrangements "subject to certain contractual conditions being met"; Alphabet's CFO cited a wider $152B of "pre-commencement leases and other obligations" on Oct 28, 2026, which is in the Google DeepMind fact sheet). [sec.gov, s206.q4cdn.com]
  5. Backlog is not revenue. CoreWeave's remaining performance obligations ($132.3B) and its "revenue backlog" ($132.5B) are different measures of the same contracts at Sep 30, 2026, and Oracle's remaining performance obligations ($664B at Aug 31, 2026) run over many years. [sec.gov 1, 2, 3]
  6. Two debt-issuance totals. The Fed's "more than $680 billion by October 2026" is advanced-computing-related issuance in 2026 to October, from Bank of America and Bloomberg data; the Bank of England's "around $450 billion" is Morgan Stanley's estimate of global AI-related issuance as of early September 2026; the definitions and dates differ. [federalreserve.gov, bankofengland.co.uk]
  7. Market values are our arithmetic (closing price times the latest filing-cover share count); on Nov 25, 2026 they agree with companiesmarketcap.com within about 1% (Alphabet $3.35T here against $3.33T there, which prices all classes at GOOG's close). TSMC's is at its New York ADR price, which differs from its Taipei price. Highs, lows and drawdowns are on daily closes, not intraday prices. [companiesmarketcap.com, finance.yahoo.com]
  8. No neocloud default is on record as of the amcompute tracker's Oct 17, 2026 update; Character.AI's Chapter 11 (Oct 12, 2026) is an AI application developer's, not a GPU cloud's. [amcompute.com, cbsnews.com]
  9. Ratings. S&P's BBB- for Oracle (Jul 9, 2026) is one notch above speculative grade; a negative outlook from Moody's is not a downgrade. [fortune.com, computing.co.uk]
  10. Capacity trackers count different things. Epoch AI estimates IT power at AI-specialised sites from imagery and covers about 43% of global AI compute; CBRE covers eight primary North American markets; JLL (North America) and Cushman & Wakefield (the Americas) count all markets, so their under-construction totals (7.5 GW, 66 GW and 37.7 GW in mid-2026) are not one series, and JLL and Cushman & Wakefield do not say whether their gigawatts are IT load or utility power. CBRE's release prints its H1 2026 supply as "10.9 megawatts (MW)". [epoch.ai · cbre.com · jll.com · cushmanwakefield.com]
  11. Requests are not load. ERCOT's 438 GW (June 2026) counts large-load requests; ERCOT's CEO called its own 2032 forecast "higher than expected future load growth", and Southern Company said it will "probably not" land its 75 GW pipeline; utilities' "contracted" figures (AEP 84 GW, Dominion over 12 GW, Southern 21 GW) use different definitions. [ercot.com 1, 2 · utilitydive.com]
  12. GPU price indexes are not interchangeable. Silicon Data publishes standardized rates in separate neocloud and hyperscaler tiers; Ornn uses executed on-demand trades only; AWS Capacity Blocks are list prices. On B200 alone they read $6.99 (Silicon Data, Nov 25), $9.07 (Ornn, Nov 24) and $14.21 per GPU-hour (AWS list), so series cannot be spliced across sources. [silicondata.com · data.ornn.com · aws.amazon.com]
  13. Memory prices. TrendForce's spot page states no unit, and spot prices differ from contract prices; its quarterly percentages here are measured changes for past quarters, while its projections for coming quarters are left out; HBM is priced in annual supplier contracts and no public HBM price index was found. [trendforce.com, trendforce.com]
  14. TSMC revenue is in New Taiwan dollars, unaudited monthly, and covers all products; "HPC" is TSMC's platform category, broader than AI accelerators. [investor.tsmc.com, pr.tsmc.com]
  15. Moratoria. New York's statewide moratorium is an executive order covering state permits for sites of 50 MW or more, with no fixed end date; the one-year bill passed on Jun 4, 2026 had no recorded signature on the Senate's page on Nov 25; Maine's bill was vetoed; no tracker counts local moratoria nationally. [governor.ny.gov · nysenate.gov · legislature.maine.gov · datacenterwatch.org]